Date:  1-5-2012
Number of Hours:  4.00
Manual Reference:  W06
Brief Description:  Flaps, final assy

Installed right flap hinge and finished pilot drilling. Finished updrilling both flaps. Disassembled and deburred all parts.

Confirmed all internal structure was satisfactory prior to closing. Clecoed flaps back together and riveted.

This completes sheet ONX-W06, Flap Details.

Total flap constuction time: 14 hours

Moving to aileron construction next, sheet ONX-W04.
' style=

Flaps complete

Flaps complete

' style=

Flaps updrilled

Flaps updrilled

' style=

Installing flap hinge

Installing flap hinge